We are Moving!

We have obtained some land 1 1/2 acres on the Broxton highway just outside the city limits of Hazlehurst, and God has provided a 36 ft x 80 ft. Chapel Trailer donated to the Church. We have set it up and got the blocks under it. We still have plenty of work to do and it needs repaired and some remodeling done. But it is something to work with, and for that we give God the Glory for all he has done. Keep coming back to see updated pictures and information concerning The Church of God at Hazlehurst Georgia.


GREETINGS TO ALL,

I wanted you to know where we are at with the building progress. We have gutted all the cieling in the sanctuary and rewired the lighting circuits. We had to tare out 20 sheets of sheet rock off the walls because they were soaked from water shot on the fire that caused the damage in the first place. We are in the process of putting the air duck back in as new duck work, and waiting on a part to put into the damper. Then we will be hanging sheet rock on the cieling and painting the walls of the sanctuary and then spraying texture on the cieling. So, still lots of work to be done yet. So, Please keep us in your prayers. I'm going to try an put a pick on this page so you can see something of whats going on, God Bless,

Brother Rick Razsi


Update for Jan 2010

Greetings, Just to let you know, that the work has come to a stand still right now. People have to work and pay the bills and thats what I'm doing right now, working and trying to get cought up on those bills. Hopefully, we will be back at work soon. keep us in your prayers.


Greetings once more,

I just wanted to inform you we got the sheet rock mudded, and we got the ceiling leveled up and ready for rock. Getting the walls ready for the primer to go on. If your in the neighbourhood please stop buy and see us. I need a reason to take a break anyway, lol.


This is our Church remodel update from Nov 31st, 2009.

We have been working hard and we have gotten the sheet rock up on the ceiling and mudded and the popcorn texture is blown and the lights are up and burning. The walls are painted out and finished, and the crown molding is almost finished. All we will need is the rugs installed and the pews put in and the Sanctuary will be finished. We still need a septic tank installed, vinyl siding put on the walls outside, and some porches built. I was going to put picks on the web page but there too big to download. So you'll just have to come bye and see it for yourself when its done. Keep us in your prayers, and Keep in touch with us to read more later.


Update June 13th, 2010

Well, We are back at work again. The Sanctuary is finished and I'm outside putting on vinyl siding on the church. Its a tan brown siding with a deep burgandy trim color. It looks beautiful and I'm excited to keep working and get Gods church finished so he can get souls into it and get them saved, Praise God!! HE'S COMING BACK SOON AND WE HAVE A LOT OF WORK TO GET DONE. PLEASE PRAY FOR US, AND IF YOU WOULD LIKE TO DONATE TOWARD THE WORK AND FUNDS OF THIS PROJECT, You will find my address inside the following web page. Thanks so much, and God Bless. Brother Rick




Progress